|
A Work in Progress
I-5/I-805 Project Opens
By David Silva
Workers recently completed the northbound portion of San
Diego's Interstate 5/Interstate 805 widening project, a $175
million effort the California Department of Transportation
hopes will alleviate chronic congestion on the interchange
- at least for a time.
The project will add a bypass from the I-5 and I-805 merge
to the Del Mar Heights Road Interchange. The goal - for now
-- is for the bypass to be used primarily by trucks using
the first two lanes north of the junction, thus relieving
the pressure the slower-moving vehicles create at the bottleneck.
Truck drivers will not be required to use the bypass. The
project also includes the addition of a high-occupancy-vehicle
lane on the southbound I-5 at Carmel Mountain Road, and auxiliary
lanes on both freeways.
Construction
started in March 2002. The new northbound lanes opened to
traffic in February, although the southbound portion won't
be completed until at least fall 2007. Caltrans architects
designed the expansion, and Yeager Skanska of Riverside is
the general contractor.
"Overall, we're getting very positive feedback from the public
on the project," said Mohammed Khan, senior resident engineer
for Caltrans. "More than 270,000 vehicles a day pass through
this junction in every direction. Interstate 5 is the lifeline
for northern San Diego. The public demand to relieve congestion
here was huge."
Just how much the widening project will relieve congestion,
Khan said, is uncertain. Given such variables as traffic growth,
the impact on the system by other freeway improvements and
the fact that the studies on which the project was based are
more than 15 years old, accurate predictions how the project
will affect traffic is almost impossible.
"It makes sense to reevaluate the project when it's finished
to see if a truck bypass is the best use of the improvements,"
Khan said. "That decision will be made sometime in spring
2007."
The fickle nature of Southern California traffic essentially
made the design of the widening project a work in progress.
As time passed from the 2002 start date of construction and
Caltrans laid plans for separate freeway projects -- most
notably a proposed widening of the I-5 from San Diego all
the way to Oceanside -- Yeager Skanska found itself confronted
with numerous change orders, said Kurt Thomas, project superintendent
for the firm.
"We basically redesigned the whole job to accommodate the
future widening improvements," he said, laughing when asked
whether the project presented significant challenges. "Caltrans
hit us with a change order for an 84-inch steel casing with
an entrance pit 25 feet deep that we had to jack under the
freeway. This had to be done on one side of the freeway in
order to build a retaining wall eight-tenths of a mile long
and seventy feet high on the other side.
"We had built this job across Los Peñasquitos Creek, and
that had some environmental challenges such as water pollution
and stormwater control."
The project is the first major Caltrans undertaking to fall
under a new regulation requiring environmental remediation
of any polluted runoff into a natural body of water. Yeager
Skanska built four bridges across Los Penasquitos Creek and
dropped nine concrete piles - the largest 12 ft. in diameter
- into the creek. According to Khan, the mesh surfacing of
the piles should filter pollution from the water.
|
Interstates
5/805 widening project by the numbers
|
| Total
amount of concrete for pavement: |
60,000
cubic meters |
| Total
number of lane miles this represents: |
20 |
| Steel
in bridges: |
Close
to 9 million kilograms |
| Earth
displaced: |
Close
to 800,000 cubic meters |
| Average
number of workers on project: |
250 |
| Average
daily number of commuters passing through interchange
in 1991: |
75,000 |
| Average
number today: |
270,000 |
|