|
Strengthening the Sewer System
Oxnard Upgrading to Keep Up With
Population Boom
Two general contractors are adding about 45,000 ft. of
new sewer interceptor pipes. Another contract calls for
a new headworks facility to come on line late next year.
By Kathy Lee Scott
Oxnard's wastewater department is in the midst of a $100
million project to upgrade the headworks portion of its treatment
plant, replace or add roughly 10 mi. of new sewer pipes and
eliminate five lift stations in its sewer collection system.
|
|
|
The two contracts
of the Redwood Trunk Sewer Project will replace about
47,000 ft. of sewer interceptor pipes and be completed
in November (photo courtesy of city of Oxnard).
|
To service its burgeoning population-the Ventura County city
has added 65,000 residents in the last 20 years, Oxnard's
city council approved the project with funding from developer
fees ($30.1 million) and $71.4 million worth of 30-year revenue
bonds. System improvements are expected to handle Oxnard's
wastewater needs for several decades.
The major upgrade to the 102-year-old city's infrastructure
includes three main contracts:
- The two contracts of the Redwood Trunk Sewer Project will
replace about 47,000 ft. of sewer interceptor pipes. The
$33.3 million southern half of the sewer project is slated
to be completed in September, while the $21 million northern
part should be done in November.
- The pipes will carry wastewater to a $40.2 million headworks
(the third contract) being built just north of the existing
sewage treatment plant on Perkins Road. The new headworks
will come on line late next year.
"We got a little behind schedule," said Bob Stier,
area manager for Chesterfield, Mo.-based Affholder Inc., one
of the two general contractors awarded the sewer project.
The other GC is Sahuarita, Ariz.-based Don Kelly Construction
Inc.
"We ran into different material than we expected,"
Stier added.
The crews encountered wood and steel debris, which was mined
out by a tunneling machine, Stier said.
The headworks facility will remove much of the larger solids
from the influent via four mechanical bar screens and a grit
chamber before it is processed in the existing treatment plant.
A state-of-the-art odor control facility will absorb odorous
gases from the air vented from the various operating areas
before releasing it to the atmosphere. The odor control facility
is part of the headworks contract.
The existing headworks will remain in service until the new
one is finished, said Mark Moise, operations manager of the
wastewater division. Then part of it will be converted to
a plant drainage system, he added.
Affholder crews are microtunneling the southern portion of
the sewer system, which entails remotely guiding a Soltau
boring machine to carve out a tunnel and install new piping.
This section of the project encompasses almost 5 mi. of sewer.
"They dig access pits for the tunnel-boring equipment,
pour concrete for a base and line them with steel sheeting,"
said George Pendergrass, project manager of Concord-based
Harris and Associates, the program manager overseeing the
project. "After tunneling, they use a hydraulic ram to
push the pipe."
Every 900 ft., the machine bores another pit, Stier said.
Pendergrass said microtunneling is the best way to install
long lengths of pipe accurately.
"It's also the best way to lay pipe in a high-water
table location," said Oxnard planner Gary Sugano.
The 42- and 60-in. Hobas pipes being installed lay about
30 ft. below ground and resist degradation from sewer gases,
Stier said. The plastic composites are immune to sulfuric
acid, Pendergrass added.
Don Kelly Construction has been using traditional open-cut
methods to lay 3.8 mi. of sewer lines along the northern section
of the system.
"We'll finish on time," said Scott Gossard, Kelly's
project manager.
The new pipelines will connect to the city's new 20,000-sq.-ft.
headworks, designed by Malcolm Pirnie of Carlsbad and built
by Lake Forest-based ARB Inc. Construction of the headworks
facility began in September and is scheduled to be finished
in late 2006, Moise said.
"We initially wanted to construct it with the sewer
system, but had to rebid it," Moise said. "The city
engineer's initial estimate for the job was too low because
concrete and rebar costs came in higher than expected."
The new facility will handle peak wastewater amounts of up
to 80 million gallons per day. The existing headworks processes
between 22 mgd and 30 mgd.
ARB industrial division manager Bob Zaiser said crews are
using a shoring system to counter the high water table of
about 7 ft. at the site.
The incoming pipes will join the headworks 17-ft. lower than
the existing headworks because the lift stations were removed.
Crews are digging to 40 ft. below grade to construct the initial
receiving area.
"We excavated around 60,000 yds. of soil," said
Mike Hoban, ARB's project manager.
|