|
Sacramento City Hall Renovation, Expansion
Enters Final 90 Days
Refurbished 95-Year-Old Building
Will Have 5-Story Addition
The restoration cost about $11 million of the total $60
million price tag. The new 267,000-sq.-ft. administration
building includes an underground parking garage for 170
cars and a precast concrete-pile foundation and steel frame.
Exterior materials include precast concrete, stone, brick
and metal panels.
By Robert Carlsen
|
|
|
A plaza separates
the new five-story, 267,000-sq.-ft. administration building,
right, from the three-story, 39,000-sq.-ft. city hall
structure (photo courtesy of the city of Sacramento).
|
The City of Sacramento's desire to centralize all its employees
scattered throughout downtown into one general location precipitated
the construction of a new government complex.
And since an earlier proposal to seismically upgrade the
95-year-old City Hall was going through the budget approval
process, officials decided to place all government near the
historic landmark.
The plan was, in government-speak, to "create an enduring
civic center that enhances the historic City Hall." Having
one location, between 9th and 10th and H and I streets, would
also alleviate the need for leased office space and "be
more convenient for customers of the city," according
to the city's Web site.
Sacramento-based David S. Taylor Interests is the development
manager on the dual project of restoring City Hall and constructing
the new administration building.
Fentress Bradburn of Denver is the exterior design architect
for the new administration building and San Francisco-based
Chong Partners Architecture worked with Architectural Resources
Group of San Francisco on the City Hall building restoration
and also did the interior design on the new building.
Demolishing an adjacent firehouse and an outdated annex building,
which was built in 1939, took place in February 2003. There
was also an underground tunnel connecting City Hall and the
annex that needed to be sealed off.
The demolition of the annex also opened up the north side
of the historic City Hall for the first time in more than
60 years.
The new annex-or administration building- measures 267,000
sq. ft. It is five stories, including an underground garage
for 170 cars, and features a precast concrete pile foundation
and steel frame. Exterior materials include precast concrete,
stone, brick, curtainwall and metal panels.
A new plaza area will connect the administration building
to City Hall.
The City Hall restoration, which will cost about $11 million
of the total $60 million dual-project price tag, was a complete
inside-and-out job, according to E.C. Looi, project manager
for the city's Public Works department. With the building's
historic significance in mind, Looi said he hired the renowned
historic preservation consulting firm, ARG.
One of the major challenges of City Hall part of the job
entailed seismic upgrades on the 39,000-sq.-ft., three-story
structure, including driving 32 micropiles 60 to 70 ft. down
through the foundation (with 12-ft. overhead clearance at
some locations), and the replacement of some brick and terracotta
on the exterior skin.
The interior restoration also included removing all the original
stone floors and walls and cataloging placement. Masonry craftsmen
also installed new marble wainscoting. The goal, according
to ARG's David Wessel, was to keep the interior as original
as possible.
Jeff Warner of Chong Partners said the whole concept of the
restoration master plan was to return the building to its
original state. "It's a beautiful wedding cake of a building,"
he said. "Through the years, there have been a lot of
additions and it really didn't improve its appearance. So
we took it back to its original look as well as giving it
another 100 years of life."
Looi said the only change to the original design plan was
relocating the main council chamber from the old building
to the new administration building and remodeling the old
chamber into a hearing room.
Bryan Amarel, project manager for the general contractor,
Hensel Phelps Construction Co., said a problem popped up in
April 2003 when prehistoric American Indian artifacts were
discovered during excavation for the parking garage. The city's
onsite archaeologist immediately stopped excavation until
the investigation was completed in accordance with the State
of California Environmental Quality Act.
The construction schedule was delayed 10 weeks.
"This was my first historic restoration project and,
obviously, the delay brought some challenges," Amarel
said. "You've got coroners, archeologists and city people
all around, and here are the construction workers just watching."
Amarel said that with any project such as this, where workers
don't know what's behind the walls-or under the ground, "you
try to keep up the momentum. It's tough. With a 100-year-old
building, you can never be sure what's behind the walls. You
can speculate, but you really don't know. So you proceed slow,
but steady."
Amarel said workers also discovered the historic clock tower
of City Hall to be slightly (about 1 ft.) askew. "We
called it the Leaning Tower of Sacramento," he added.
He said the original builders caught the mistake and overbuilt
the western side of the tower to compensate for the difference
in elevation.
Hensel Phelps replaced the roof with a new "energy-saving
single-ply roof.
Amarel also said contractors righted a sizeable wrong: The
original City Hall had a men's restroom that took up about
half of the first floor, while the ladies' restroom was a
single stall. "We evened things out there," he said.
Amarel said he's now working toward the April 29 completion
date.
"We're identifying any loose ends, trying to keep the
punch list to a minimum," he added. "It's part of
our quality-control program."
|