|
Cutting-Edge Campus for Caltrans: District
7 Headquarters to Debut Next Month
The 1 million-sq.-ft. complex in
downtown Los Angeles has a giant cantilever hanging 40 ft.
above the sidewalk; a three-story-high, neon art piece; and
the largest solar energy system of any building in North America.
By Greg Aragon
A new downtown Los Angeles landmark--located between the
wavy, reflecting steel panels of the Walt Disney Concert Hall
and the alabaster and stained glass of the Cathedral of Our
Lady of the Angels-is six weeks away from opening its doors.
The $168 million headquarters for Caltrans District 7, a
13-story building, is one block from Los Angeles City Hall,
on the northern edge of the city's skid row.
"It is an innovative, modern avant-garde building,"
Pavel Getov, project architect with Santa Monica-based Morphosis,
said of the 1 million-sq.-ft. complex. "[Caltrans] was
not looking just for a building, it was looking for design
excellence."
Caltrans is certainly getting a building that commands attention.
The L-shaped structure has a giant cantilever dangling 40
ft. above the sidewalk off its north wall, a 200-ft.-long,
three-story-high, neon art piece wrapping around an outdoor
"urban lobby," and 1,500 photovoltaic panels--the
most on any building in North America--speckling the south
wall.
The project is headed by First and Main Design/Build Associates,
a design/build entity of the Irvine office of Clark Construction
Group; Morphosis (design architect); and Los Angeles-based
Gruen Associates as associate architect.
The design/build team also includes the developer, Urban
Partners of Los Angeles; Los Angeles-based John A. Martin
& Associates (structural engineer); and Los Angeles-based
Ove Arup & Partners California (mechanical/electrical,
fire protection and telecommunications engineer.) The state's
Department of General Services is the owner.
Slated for an Oct. 26 grand opening, the 750,000-sq.-ft.
building and 1,142-space, 400,000-sq.-ft. underground parking
garage is bounded by First, Second, Main and Los Angeles streets.
Because the stocky structure spans an entire city block,
Getov said that Morphosis went with a different approach in
planning the interior.
"This building is actually a high-rise that is laying
down," he said. "It is a horizontal high-rise in
a way in which we have two cores instead of one core. One
core is very traditional with an elevator that stops at every
floor, but the other one is with an elevator that stops at
every third floor."
He said it was designed this way to increase communication
between floors via the stairs, thus "stimulating human
interaction between different parts of the building."
The headquarters was built using 30,000 cu. yds. of concrete,
10,500 tons of structural steel and 500 tradespeople at its
peak. It was constructed with a concrete foundation and a
steel moment-resisting structural frame.
Construction began in March 2002 on a tight, 29-month design/build
schedule. Jim Hammer, Caltrans' deputy of administration,
said that the jobsite required extremely "close coordination,
quick decision making and collaboration" at all times.
"The advantage of the design/build process is that it
fosters a true team effort, rather than a combative change-order
game common in design/bid/build delivery," Hammer added.
"By recognizing each individual team member's ability
to contribute, the project staff-from the state, tenant, designer
and contractor-defined goals and set up activities to accomplish
them on a fixed time frame."
Marc Kersey, Clark's project executive, was well aware of
the project's fast-track timeline. "We had a shotgun
start," he said. "From the beginning, design and
construction significantly overlapped."
Tasks such as excavation, placing foundations and ordering
certain materials became an exact science.
"You've got to procure structural steel that takes six
months from the time you finish the design until the time
you get it to the job," Kersey said. "So just four
months after we started the design, we had to have a 100-percent
complete structural design so that we could order the structural
steel in time to start in November 2002."
The project is currently substantially complete, with crews
finishing up punch-list items. When it opens next month, the
complex will house 1,857 Caltrans employees and approximately
425 Los Angeles Department of Transportation employees.
Features will include an auto shop, warehouse, teleconference
room, public cafeteria and a child-care facility for employees
and the public. Approximately 1,100 perforated, operable panels
in front of the building windows will open and close with
the touch of a computer. The panels will allow clear views
when that side of the building is in the shade and close when
the side is exposed to direct sunlight.
The building's other exterior panel system, the photovoltaic
panels, will not only generate 84 kilowatts of power back
into the grid, but will also act as a sun screen for the south-facing
windows.
The existing Caltrans office building across the street was
first built in 1949 and will be demolished when the new facility
is completed.
|